Executive Dashboard
Shiva Green Energy · 5 TPH Biomass Pellet Plant · Lean Base Case · No Solar · Aug 2026
Project IRR (10-Year)
108.9%
Equity IRR: 231.9%
Unlevered project return on total capital. Target > 14% WACC.
Project NPV @ 14%
₹39.1 Cr
Discount Rate 14%
Simple Payback
Yr 1.1
Project FCF basis
Year 1 Revenue
₹18.0 Cr
75% util · 22,500 T
Year 2 Revenue
₹23.5 Cr
95% util · steady state
Year 2 PAT
₹6.82 Cr
Margin: 29.0%
DSCR (Year 2)
9.58x
Target > 1.5x (CGTMSE)
Revenue vs Total Cost
10-Year trend · ₹ Crores
Funding Structure
Equity vs Debt · ₹6.25 Cr total
Partner Equity
₹2.50 Cr
40.0%
Debt (CGTMSE)
₹3.75 Cr
60.0%
EBITDA & PAT Trend
Operating profitability · ₹ Crores
CAPEX Breakdown
Uses of funds
Cumulative Project Cash Flow — Payback Visualization
Payback at Year ~1.1 · ₹ Crores
Investment Committee Recommendation
GO WITH CONDITIONSOverall Project Data Confidence Score: 7.0 / 10 — rises to 8.5+/10 once offtake LOI, final quotes, incorporation and lease are complete.
Convert partnership firm into a Private Limited Company with clear shareholding.
Execute clean, registered 30-year lease deed for the 10–12 acre parcel.
Obtain at least one written vendor registration/LOI from NTPC, Rosa or equivalent TPP.
Finalise machinery quotation from proven OEM for 5 TPH line within ₹3.0–3.5 Cr envelope.
Secure CGTMSE-backed term loan + WC sanction with DSCR covenant ≥ 1.50x.
Maintain minimum ₹1.4 Cr working capital buffer at COD; do not treat WC as residual.
Complete environmental / consent-to-establish clearances before civil works.
(Optional) Explore Phase-2 500–1000 kW solar once Year-1 cash flows are proven.
Bank Financeable
CGTMSE eligible — with proper DPR, offtake evidence, Udyam registration, DSCR covenant
Investor Attractive
More attractive at 5 TPH than 2 TPH — better scale economics for strategic and financial investors
Key Risk
Feedstock supply + offtake volume shortfall are the two highest-impact risks. Mitigate with contracts before drawdown.
Model Notes & Assumptions
- 1.Solar has been dropped from the Base Case. Power cost is full grid (₹1,100/tonne).
- 2.Carbon credits treated as Upside only — not included in Base P&L.
- 3.All amber cells on Assumptions sheet are editable inputs — changes recalculate instantly.
- 4.Model uses conservative-to-realistic assumptions for bankability.
- 5.Entity currently partnership firm — conversion to Pvt Ltd recommended before large debt.
- 6.CAPEX scaled non-linearly: machinery ~2.5×, civil ~1.9×, WC ~3.5× vs 2 TPH baseline.
- 7.10-year explicit forecast with simplified debt amortisation. No terminal value in IRR/NPV.